Greensburg Board of Aviation Commissioners

The Greensburg Board of Aviation Commissioners met on Monday.

There was a financial report given to the board. The total funds for all 3 accounts is $713,424.92.

Paul Shafer with BF&S gave an update on construction. There has been no further construction due to it being winter. The paving and lighting phase has had good movement, however they want to rewrite the recommendation for awards and create 2 parts. INDOT is putting in a new traffic signal near the airport which would be an obstruction to the current runway. This will no longer be a problem once the new runway is built and open.

There was an update on the airport. All the hangars are full. They are still selling fuel, but sales are down due to cold weather.

The bills were approved.

Morgan Schofield

WTRE News

All Rights Reserved

Post Ad 2